Project Overview
A joint venture of AEP Renewables and BP Wind Energy, the 248-megawatt (MW) Cedar Creek II wind farm is located near New Raymer, Colorado. It generates enough clean energy to power about 84,000 homes. The project’s entire power output is sold under a 25-year contract to Public Service Company of Colorado.
To view more AEP Renewables projects, click here.
Facts At A Glance
Project Type
Wind Turbine
Project Name
Cedar Creek II
Project Location
Colorado
Status
Operating
Commercial Operation
2011
EPC
Blattner Energy
Owner
AEP Renewables, BP Wind Energy
Operator
AE Power Services LLC, a subsidiary of BP Wind Energy
Wind Farm Rating
248 MW
Number of Wind Turbines
123
Turbine Rating
1.6 MW - 2.5 MW
Rotor Diameter
82.5m - 90m
Hub Height
80m
Turbine Manufacturer
General Electric, Nordex